Asbestos

Fibers released when asbestos-containing material is disturbed during renovation or demolition. 29 CFR 1926.1101 sets a permissible exposure limit of 0.1 fiber per cubic centimeter as an 8-hour average.

Where it shows up

  • Pipe and boiler insulation in older buildings
  • Sprayed-on fireproofing and textured ceilings
  • Floor tile and mastic
  • Roofing and siding materials

Controls, most effective first

Work down the list. Rely on PPE only for the risk the controls above it cannot remove.

LevelControl
Eliminate or substituteHave a survey done before renovation or demolition, and abate before other trades start
EngineeringRegulated areas, wet methods, and HEPA-filtered equipment for asbestos work
AdministrativeStop work if you find suspect material, and report it
Only trained and qualified workers handle asbestos
Treat thermal system insulation and surfacing material in buildings built in 1980 or earlier, and asphalt and vinyl flooring installed by 1980, as asbestos until tested
PPERespirator and disposable coveralls for asbestos work

PPE to list on the JHA

Respirator1926.103

OSHA standards

CitationTitle
29 CFR 1926.1101Asbestos

Federal OSHA construction standards. State plans can be stricter, and owners or contracts can add requirements. This page is general information. Check the full standard for your work.